    We believe we can add reliable information to your preparation of a reasonable bidding quotation. We give you a reference “current” reasonable price (All material, labor, and equipment base price preferred in Addis). We are showing you the Engineering Estimates for the Direct rate for Road Construction.

    If your need is not in the list below Make a Request via constructionproxy@gmail.com

    NB:1.  this cost is only for your reference. Profit Loss and overhead are not part of this Estimate this is only a Direct Rate. 

    Item No.Item DescriptionUnitRate
    Bill No. 2Clearing and Grubbing
    201.01Clearing and grubbingha280,512.97
    21.05Removal and grabbing of large trees and tree stumpsNo10,000.00
    Bill No. 3Drainage
    31.01Drains
    32.01Excavations;
    32.01a(iv)Soft material irrespective of depthm3112.75
    32.01(b)excavation of hard material irrespective of depthm3674.70
    32.02Backfilling
    32.02(a)Using excavated materialm3618.41
    32.02(b)Using imported selected granular materialm31,692.96
    32.03Concrete pipe culverts
    32.03(ii)(1)Concrete pipe on Class B bedding, nominal diameter 760mmLm15,499.36
    32.03(ii)(2)Concrete pipe on Class B bedding, nominal diameter 910mmLm14,421.08
    32.03(ii)(3)Concrete pipe on Class B bedding, nominal diameter 1060mmLm16,696.28
    32.03(ii)(4)Concrete pipe on Class B bedding, nominal diameter 1220mmLm20,513.77
    Cocrete curbLm1,275.78
    Masonry gutter with a cross section of (0.8*0.85)Lm10,088.41
    32.07Cast Insitu concrete and formwork
    32.07(b)Class C concrete including formworksm315,412.12
    32.07(g)Class A concrete including formworksm318,332.05
    32.10Steel reinforcement
    32.10(b)High tensile steel reinforcement in Culverts (Grade 60)ton191,869.42
    34(01)Stone Pitching
    34.01(b)(II)Grouted Rubble Pavedwaterwaym31,829.88
    34.02Riprap
    (a)Packed Riprapm31,445.50
    34.03Stone Masonary Walls
    34.03(a)Dry stone masonary wallsm3
    34.03(b)Cement mortared stone walls, Class ‘B’m35,948.44
    Bill No. 4Earthworks
    41.01Removal of unsuitable material
    41.01Removal of unsuitable material
    (b)In layer thickness exceeding 200mm (6km hauling distance)m3360.62
    41.03Road bed Preparation and the compaction of Material
    41.03(b)Road Bed Preparation Compaction to 93% of modified AASHTOdensitym294.83
    42.01Cut and Borrow to Fill :
    42.01a(ii)Cut and borrow to fill, compaction to 95% AASHTO T-180m3328.07
    42.01(c)Rock (hard) to fillm31,180.31
    42.03Cut to Spoil material obtained from:
    42.03(a)Common (normal) Excavation (6km Spoil dits.)m3751.74
    42.03(b)Intermediate Excavation (6km Spoil dits.)m3921.76
    42.03(c)Rock (hard) Excavationm3822.71
    44.05Improved subgrade
    44.05(a)Improved Subgrade G20 (Mat. From 6Km )m31,468.64
    44.05(b)Improved Subgrade G7 (Mat. From 1Km )m31,912.78
    45.01Furrow ditchlm180.33
    Bill No. 5Subbase, Roadbase and Gravel Wearing Course
    5,400.00GRANULAR COURSES
    51.01(a)iGravel subbase layer, 97% MDD, AASHTO T-180 (Material from 6km)m33,720.41
    52.01(b)ICrushed Aggregate Base course compacted to 98% of modified AASHTO density (Material from 10km)m35,254.23
    Bill No. 6Bituminous Surfacing
    6,000.00BITUMINOUS SURFACING
    61.01Prime coat
    (a)MC-30 cutback bitumenm2148.29
    6,400.00Bituminous Road Bases and Surfacing
    surface treamentm2510.69
    64.0250mm Asphaltic surfacing with (penetration grade 60/70 bitumen
    (a)Continous grading (medium)m21,578.08
    Bill No. 8Structures
    8,000.00STRUCTURES
    81.02Excavation for Structures
    (a)Excavation of soft material situated in the following successive ranges:
    i0m to 2mm3579.82
    Irrespective of Depthm3621.60
    (b)Excavation of hard (rock) material irrespective of depthm31,339.20
    81.05Backfilling to Excavation
    (a)Using excavated materialm31,129.01
    (b)iimported granular materialm32,115.23
    (b)iihand laid rock fill material between wing wallsm31,445.50
    (b)iiihand laid Riprap on exposed face of backfillm31,445.50
    82.02Formwork for indicated class of finish
    (a)conecrete footing of abutments and wing walls
    iconecrete footing of abutments and wing wallsm2
    iisoffit of concrete deck slabm2
    (b)Cast Insitu concrete and formwork
    iside walks in main slab,Visible part of girder,on abutmentm24,224.72
    83.01Steel reinforcement for structure
    (a)(i) Mild steel bars (Grade 300)ton166,058.40
    (b)(ii) High yield stress steel bars (Grade 420)ton202,808.40
    84.01Cast in situ concrete
    (a)(a) Class C-30 in all superstructure parts, abutument & wing wall foundations and walklwaysm329,820.11
    (b)(b) Class C-20 in abutument &wingwalls footing padsm320,845.71
    87.03Bearings
    (c)Elastomer BearingNo.30,780.91
    87.07Concrete parapetslm12,655.17
    87.19Drainage pipes and weep holes
    (a)Drainage pipes (20 cm internal dia pvc)m/No500.00
    89.01Stone Masonry Walls
    (a)Cement-mortared stone masonry walls (Class B)m34,729.62
    Bill No. 9Ancillary Works
    9,000.00ANCILLARY WORKS
    91.01Gabions
    91.01(a)(a) Gabion boxes 1m by 1m cube with galvanized wire meshm32,941.71
    92.01Delineators, markers and kilometer posts
    (a)Delineator posts/guidepost, reinforced concreteno.1,434.68
    (c)Kilometer posts, cement concreteno.1,434.68
    94.01Sign faces with painted background, symbols, lettering and borders in Engineering grade retro-reflective material with signboard constructed from:
    94.01(a)iSign face with area not exceeding 2.0 sq.m fixed on postno.2,170.99
    94.01(a)iiSign face with area exceeding 2.0 sq.m but not exceeds 10 sq.m fixed on postno.26,051.88
    94.02Sign supports:
    94.02(a)Sign Support/Sign post, Class ‘A’ concreteno.4,023.00
    94.03Road Sign Footing
    94.03 (a)Excavation for footing of Sign Supportm3112.75
    94.03 (b)Backfilling for footing of Sign Supportm31,692.96
    94.03 (c)Class ‘A’ concrete for footing of road sign supportm39,747.72
    9,500.00Road Traffic Markings and Road Studs
    95.01(a) iWhite unbroken 10cm lineKm.5,459.44
    95.01(a) iiwhite broken (2.5m dash, 7.5m gap) 10cm lineKm.3,546.81
    95.01(b)Yellow unbroken 10cm lineKm.5,459.44
    9,900.00SIDEWALK
    99.01(a)Concrete tiles of 50mm thick including the necessary jointing worksm2487.39