Engineering Estimate for Road Items: Auguest 15, 2024

    We believe we can add reliable information to your preparation of a reasonable bidding quotation. We give you a reference “current” reasonable price (All material, labor, and equipment base price preferred in Addis). We are showing you the Engineering Estimates for the Direct rate for Road Construction.

    If your need is not in the list below Make a Request via constructionproxy@gmail.com

    NB:1.  this cost is only for your reference. Profit Loss and overhead are not part of this Estimate this is only a Direct Rate. 

    Item No.Item DescriptionUnitRate
    Bill No. 2Clearing and Grubbing
    Scope This Division covers the clearing of the Site and grubbing necessary for the construction of the Works covered by the Contract, in accordance with these Specifications, and the removal and disposal of materials resulting from clearing and grubbing. This work shall also include the preservation from injury or defacement of all vegetation and objects designated to remain. [ERA 2002]
    201.01Clearing and grubbingha146,686.97
    21.05Removal and grabbing of large trees and tree stumpsNo10,000.00
    Bill No. 3Drainage
    Scope This Division covers all work in connection with the excavation and construction of open
    drains, subsoil (Sub surface) drainage and banks and dykes at the locations and to the sizes,
    shapes, grades and dimensions as shown on the drawings or as directed by the engineer, and
    the test flushing of subsoil drains.
    It also covers the cleaning of open drains and the repairing of subsoil (Sub surface) drainage.
    In special circumstances this work may be executed outside the road reserve.
    It also covers the clearing of existing culverts, including amongst others the removal of all
    undesirable materials that have accumulated in and around Inlet and outlet structures and in
    the barrels of the culverts. [ERA 2002]
    31.01Drains
    32.01Excavations;
    32.01a(iv)Soft material irrespective of depthm3103.27
    32.01(b)excavation of hard material irrespective of depthm3491.83
    32.02Backfilling
    32.02(a)Using excavated materialm3538.55
    32.02(b)Using imported selected granular materialm31,417.64
    32.03Concrete pipe culverts
    32.03(ii)(1)Concrete pipe on Class B bedding, nominal diameter 760mmLm13,835.54
    32.03(ii)(2)Concrete pipe on Class B bedding, nominal diameter 910mmLm12,580.85
    32.03(ii)(3)Concrete pipe on Class B bedding, nominal diameter 1060mmLm14,832.34
    32.03(ii)(4)Concrete pipe on Class B bedding, nominal diameter 1220mmLm18,238.86
    Cocrete curbLm1,145.71
    Masonry gutter with a cross section of (0.8*0.85)Lm8,964.09
    32.07Cast Insitu concrete and formwork
    32.07(b)Class C concrete including formworksm313,711.75
    32.07(g)Class A concrete including formworksm316,797.39
    32.10Steel reinforcement
    32.10(b)High tensile steel reinforcement in Culverts (Grade 60)ton190,423.87
    34(01)Stone Pitching
    34.01(b)(II)Grouted Rubble Pavedwaterwaym31,556.75
    34.02Riprap
    (a)Packed Riprapm31,081.29
    34.03Stone Masonary Walls
    34.03(a)Dry stone masonary wallsm3
    34.03(b)Cement mortared stone walls, Class ‘B’m34,948.53
    Bill No. 4Earthworks
    Scope
    This Division covers all work in connection with the preparation of the road bed, prior to the construction of the embankments or capping layers, and the preparation of the sub-grade prior to the construction of the pavement layers. [ERA 2002]
    41.01Removal of unsuitable material
    (b)In layer thickness exceeding 200mm (6km hauling distance)m30.00
    41.03Road bed Preparation and the compaction of Material
    41.03(b)Road Bed Preparation Compaction to 93% of modified AASHTOdensitym258.04
    42.01Cut and Borrow to Fill :
    42.01a(ii)Cut and borrow to fill, compaction to 95% AASHTO T-180m30.00
    42.01(c)Rock (hard) to fillm30.00
    42.03Cut to Spoil material obtained from:
    42.03(a)Common (normal) Excavation (6km Spoil dits.)m3404.04
    42.03(b)Intermediate Excavation (6km Spoil dits.)m3504.36
    42.03(c)Rock (hard) Excavationm30.00
    44.05Improved subgrade
    44.05(a)Improved Subgrade G20 (Mat. From 6Km )m30.00
    44.05(b)Improved Subgrade G7 (Mat. From 1Km )m30.00
    45.01Furrow ditchlm110.31
    Bill No. 5Subbase, Roadbase and Gravel Wearing Course
    5101 SCOPE
    This Division covers the specification of materials for, and the construction of, sub-base pavement layers including the in-situ recycling of existing pavements. [ERA 2002]
    Item No.Item DescriptionUnitRate
    5400GRANULAR COURSES
    51.01(a)iGravel subbase layer, 97% MDD, AASHTO T-180 (Material from 6km)m32,246.63
    52.01(b)ICrushed Aggregate Base course compacted to 98% of modified AASHTO density (Material from 10km)m33,271.20
    Bill No. 6Bituminous Surfacing
    6101 SCOPE
    This Division covers the application of a bituminous prime coat to a prepared pavement layer. [ERA 2002]
    6000BITUMINOUS SURFACING
    6100Bituminous prime coat
    61.01Prime coat
    (a)MC-30 cutback bitumenm2158.83
    6400Bituminous Road Bases and Surfacing
    surface treamentm2405.93
    64.0250mm Asphaltic surfacing with (penetration grade 60/70 bitumen
    (a)Continous grading (medium)m21,443.87
    6700surfacing of Bridge deck
    Bill No. 8Structures
    8101 SCOPE
    This Division provides specifications for the construction of foundations for structures including bridges, retaining walls, box and slab culverts etc. It provides in particular specifications for excavation, and back filling and for the construction of the foundation it self as well as the pile capping slabs or the caisson cover slabs. [ERA 2002]
    8000STRUCTURES
    81.02Excavation for Structures
    (a)Excavation of soft material situated in the following successive ranges:
    i0m to 2mm3344.92
    Irrespective of Depthm3418.32
    (b)Excavation of hard (rock) material irrespective of depthm3932.64
    81.05Backfilling to Excavation
    (a)Using excavated materialm3976.55
    (b)iimported granular materialm31,667.34
    (b)iihand laid rock fill material between wing wallsm31,081.29
    (b)iiihand laid Riprap on exposed face of backfillm31,081.29
    82.02Formwork for indicated class of finish
    (a)conecrete footing of abutments and wing walls
    iconecrete footing of abutments and wing wallsm2
    iisoffit of concrete deck slabm2
    (b)Cast Insitu concrete and formwork
    iside walks in main slab,Visible part of girder,on abutmentm24,094.62
    83.01Steel reinforcement for structure
    (a)(i) Mild steel bars (Grade 300)ton163,890.08
    (b)(ii) High yield stress steel bars (Grade 420)ton200,640.08
    84.01Cast in situ concrete
    (a)(a) Class C-30 in all superstructure parts, abutument & wing wall foundations and walklwaysm327,534.10
    (b)(b) Class C-20 in abutument &wingwalls footing padsm318,457.52
    87.03Bearings
    (c)Elastomer BearingNo.30,780.91
    87.07Concrete parapetslm12,245.02
    87.19Drainage pipes and weep holes
    (a)Drainage pipes (20 cm internal dia pvc)m/No500.00
    89.01Stone Masonry Walls
    (a)Cement-mortared stone masonry walls (Class B)m34,020.66
    Bill No. 9Ancillary Works
    9101 SCOPE
    This Division covers the construction of gabion walls and aprons for the construction of
    retaining walls, lining of channels, revetments, and other anti-erosion structures in accordance with the details shown in the Contract.
    ItemDescriptionUnitUnit Rate (ETB)
    9000ANCILLARY WORKS
    91.01Gabions
    91.01(a)(a) Gabion boxes 1m by 1m cube with galvanized wire meshm32,204.82
    92.01Delineators, markers and kilometer posts
    (a)Delineator posts/guidepost, reinforced concreteno.1,216.31
    (c)Kilometer posts, cement concreteno.1,216.31
    94.01Sign faces with painted background, symbols, lettering and borders in Engineering grade retro-reflective material with signboard constructed from:
    94.01(a)iSign face with area not exceeding 2.0 sq.m fixed on postno.2,069.35
    94.01(a)iiSign face with area exceeding 2.0 sq.m but not exceeds 10 sq.m fixed on postno.24,832.20
    94.02Sign supports:
    94.02(a)Sign Support/Sign post, Class ‘A’ concreteno.3,469.47
    94.03Road Sign Footing
    94.03 (a)Excavation for footing of Sign Supportm3103.27
    94.03 (b)Backfilling for footing of Sign Supportm31,417.64
    94.03 (c)Class ‘A’ concrete for footing of road sign supportm39,487.53
    9500Road Traffic Markings and Road Studs
    95.01(a) iWhite unbroken 10cm lineKm.5,459.44
    95.01(a) iiwhite broken (2.5m dash, 7.5m gap) 10cm lineKm.3,546.81
    95.01(b)Yellow unbroken 10cm lineKm.5,459.44
    9900SIDEWALK
    99.01(a)Concrete tiles of 50mm thick including the necessary jointing worksm2474.38